https://www.youtube.com/watch?v=LESdpsudU44
Two giant tunnelling machines – named ‘Florence’ and ‘Cecilia’ – pass halfway mark during excavation of the 10 mile long Chiltern tunnels
1.3 million cubic...
The HS2 rail line will go all the way to London Euston, the chancellor has said, following a report the scheme may no longer reach the capital's centre.
https://www.bbc.com/news/uk-64421566
Finally some real-world news about the project.
https://www.newcivilengineer.com/latest/hs2-lacks-support-as-project-was-not-well-planned-uk-infrastructure-tsar-says-13-01-2023/
Talented graduates have just two weeks left to apply for one of 40 places on HS2 Ltd’s coveted two-year graduate training programme, which begins in September 2023.
With a two-decade long construction programme ahead, HS2 Ltd, the company...
https://www.youtube.com/watch?v=DxGd83rzcts
In a huge feat of engineering, HS2 Ltd has delivered the world’s longest box slide to move a 12,600 tonne bridge into place over the M42 in Warwickshire.
The innovative method dramatically...
Exciting High Speed 2 opportunity at North Acton
--
Job Introduction
The Engineering Survey team is employed to deliver the geospatial capabilities required to efficiently and accurately deliver the works in accordance...
Exciting High Speed 2 opportunity at West Ruislip, United Kingdom.
------
Job Introduction
In general, the Tunnel Engineer's position is to support the tunnel technical services team in preparation for tunnelling, both TBM...
Mark Harper MP, Secretary of State for Transport, joined HS2 Ltd CEO Mark Thurston for a drive-through of the first bored tunnel at Long Itchington in Warwickshire, as momentum continues to build on the project
The 2,000 tonne TBM...
The 2,000 tonne tunnel boring machine ‘Dorothy’ sets off for second tunnel drive under Long Itchington Wood in Warwickshire
The first one-mile tunnel bore was completed in July this year – the first breakthrough on...
HS2 celebrates launch of TBM for second tunnel bore under Long Itchington Wood in Warks
The 2,000 tonne tunnel boring machine ‘Dorothy’ sets off for second tunnel drive under Long Itchington Wood in Warwickshire
The first...
HS2’s Herrenknecht TBM ‘Dorothy’ has launched for her second 1.6km long (one-mile) tunnel bore under Long Itchington Wood in Warwickshire, marking the next big milestone for construction on the northern section of Phase...
https://www.youtube.com/watch?v=2z0vAtvqjmc
From Balfour Beatty;
Astonishing 1.7 mile conveyor network will remove over one million lorry movements for HS2’s construction in the Capital.
New video shows the impressive conveyor...
"Bouygues has reportedly pulled one of its tenders for the 300M HS2 Phase One overhead catenary works contract due to competition issues arising from its merger with Equans" reports...
HS2 construction in London gathers pace as second tunnelling machine sets off underneath the capital
Hot on the heels of HS2’s first London TBM, ‘Sushila’, who set off earlier this month, the 2,000 tonnes TBM,...
HS2’s first Tunnel Boring Machines (TBMs) excavating HS2’s longest tunnels have completed the first 4 miles of their drive – from the Chiltern tunnel’s south portal to the second ventilation shaft at Chalfont St...
HS2 Ltd has opened applications for innovative tech start-ups to join its successful Innovation Accelerator programme.
The initiative, now assembling its fifth cohort, is seeking five candidates to harness the power of Artificial...
First of two 2,000 tonne TBMs (Tunnel Boring Machines) starts 5-mile journey towards Greenford from West Ruislip in West London
First machine named ‘Sushila’, after pupils nominated local teacher Sushila Hirani....