PORR - Marti Joint Venture gets the contract for Brenner Base Tunnel lot H53 Pfons-Brenner

    Carlos Kirschner
    By Carlos Kirschner

    PORR contract awarded for Brenner Base Tunnel Lot H53

    As released by PORR AG (https://porr-group.com/en/press/press-release/news/contract-awarded-for-lot-h53-pfons-brenner/) including the picture.

     

    Contract awarded for lot “H53 Pfons-Brenner”

     

    Vienna, 04.04.2023 – This is the largest construction lot in Austrian history: The construction company BBT SE has awarded the contract for the construction of the Pfons-Brenner tunnel section to a consortium of PORR Bau GmbH and Graz-based MARTI GmbH and MARTI Tunnel AG. The contract is worth EUR 959m.

    “We are delighted to be tackling this project of the century with our partner MARTI”, said PORR CEO Karl-Heinz Strauss. “The Brenner Base Tunnel is a key response to the core issue of mobility that Europe needs to address”.

    Its far-reaching expertise in tunnelling enabled PORR to win out with the best bid in the tender process. Strauss adds: “We have reorganised our team and will now complete this section quickly. As a link between Austria and Italy, the Brenner Base Tunnel needs to play its key part in the European transport network as soon as possible”.

    Full speed ahead through the mountains

    The construction of the Pfons-Brenner section (lot H53) will take around six years. The scope of the contract includes two single-track main tunnel tubes with a total length of 25.2 km. The PORR - MARTI consortium will use two tunnel boring machines (TBMs) as well as blasting. The TBMs have an excavation diameter of 10.37 m, allowing them to cover a distance of up to 30 m per day. In addition to the main tunnels, another 3.6 km of exploratory and cross-cut tunnels are planned.

    The new contract is not PORR’s only construction lot for the Brenner Base Tunnel: The company is also building the approximately 600-metre-long link between the tunnel and Innsbruck’s main railway station through the Sill Gorge with construction lot H21. Completion of the Sill Gorge section is planned for 2024.
     

    Facts and figures at a glance

    Project type: Tunnelling, specialist civil engineering
    Scope of services: Construction of two main tunnel tubes with a total length of 25.2 km plus an additional 3.6 km of tunnel sections and all inner linings
    Client: BBT SE
    Contractor: PORR Bau GmbH, MARTI GmbH, MARTI Tunnel AG
    Project duration: 70.5 months
    Contract volume:

    EUR 959m (consortium)

     

     