Norway: Statkraft Energi AS applies for the tunnel build permit for Svean power plant

    Jørn Sørensen
    By Jørn Sørensen

    Statkraft Energi AS is applying for a discharge permit for the operation of a tunnel in connection with the construction of a new Svean power plant.

    The construction work is planned in the period 2025-2027. The application describes, among other things. How the business should clean the emission water before emissions to the watercourse. The company at this time applies only for emissions to water. The disposal of masses (tunnel masses and sediments) will be assessed later in the project. 

    https://www.statsforvalteren.no/nn/Trondelag/Horinger/2024/03/statkraft-energi-as-soker-om-utslippstillatelse-for-driving-av-tunnel-i-forbindelse-med-bygging-av-nytt-svean-kraftverk/

     