On Uznam side, work continued on building of support buildings. Work continued for Tunnel Boring Machine Starter Chamber by excavation of the area.
On the other hand, on the Wolin island side, area cleared of trees and the infrastructure on the way, electric cables etc.
It is said that despite Covid-19 Chinese company CREG is on schedule for manufacture of the TBM. Manufacture is complete to large extend. In June factory acceptance tests will be performed in China.
Świna tunnel (Tunel Świnoujście) progress 04.07.2022 - 10.07.2022
Świna tunnel (Tunel Świnoujście) progress 11.07.2022 - 17.07.2022
Świna tunnel (Tunel Świnoujście) progress 18.07.2022 - 24.07.2022
Świna tunnel (Tunel Świnoujście) progress 25.07.2022 - 31.07.2022
Świna tunnel (Tunel Świnoujście) progress 1.08.2022 - 7.08.2022
Important to show development of the project.
Świna tunnel (Tunel Świnoujście) progress 8.08.2022 - 14.08.2022
late but important to show development of the project.
Świna tunnel (Tunel Świnoujście) progress 15.08.2022 - 21.08.2022
late but important to show development of the project.
Świna tunnel (Tunel Świnoujście) progress 22.08.2022 - 28.08.2022
late but important to show development of the project.
Świna tunnel (Tunel Świnoujście) progress 29.08.2022 - 4.09.2022
cover tunnel photo by: Matt Brown from London, England / CC BY