English | Spanish | Dutch
Log in

HS2: Even before the High Speed 2 project was approved, contractors had already ordered 3 Tunnel Boring Machines

 

It turns out that the contractors had already ordered the tunnel boring machines in 2019, when the HS2 project was still under review and the contractors were not given the go ahead. 

A Freedom of Information request by Britain's New Civil Engineer publication reveals that 3 TBMs at a cost of £52M were ordered by HS2 contractors. The High Speed 2 project has only been formally approved on 7 February 2020 by British Prime Minister Boris Johnson.

Reportedly HS2 Ltd, the company overseeing the project confirms that 2 of the tunnel boring machines were ordered for the C1 Chiltern Tunnels contract (contractor is Align, a joint venture of Bouygues Travaux Publics, Volker Fitzpatrick and Sir Robert McAlpine). For the time being, it has not been made public which contractor ordered the third TBM.

https://www.newcivilengineer.com/latest/three-hs2-tbms-ordered-before-oakervee-review-concluded-18-03-2020/

 

 

  • Kris Lubcek
    By Kris Lubcek

    While the High Speed 2 project was still under review and not yet approved, contractors had already ordered 3 Tunnel Boring Machines...

    https://www.newcivilengineer.com/latest/three-hs2-tbms-ordered-before-oakervee-review-concluded-18-03-2020/

    #HS2

    Three HS2 TBMs ordered before Oakervee review concluded

    www.newcivilengineer.com

    A Freedom of Information request by NCE revealed that contractors spent £52,154,038 on three items of equipment – which HS2 Ltd has now confirmed are TBMs

  • Arie van den Broek
    By Arie van den Broek

    It doesn't smell right. It shows that they already knew -somehow- they would get go-ahead even though the projects was still in review.

    The question is; how could they be so sure?

    As a matter of fact, it smells very bad.

  • Roberto Calvi
    By Roberto Calvi

    Review process and approval was only a show. Good PR work British government

  • Chu Yang
    By Chu Yang

    Corruption English government with big construction companys

  • Dave Anderson
    By Dave Anderson

    Look guys, this isn't a black and white situation. As I know it, it takes between 10 to 15 months to manufacture a tunnel boring machine. That is, for a TBM of railway tunnel size (diameter of 8-10m) EPB TBM. I might be wrong may be one or two months. But on average, that is what it takes to get such a TBM from the time you place the order.

    The construction companies are expected to start the work now. Right now. They can't just say, `OK, wait for a year for the TBM delivered before we start the work'. They take risks. They have to take risks. Yes, in all likelihood they probably got some early indication about the approval.  But still the whole thing could get cancelled and I don't know what would happen to the ordered TBMs. Maybe they have some mitigation clauses in their agreements with the TBM manufacturers but in any case they would loose some money.

    It is not a black and while situation.

  • Jorrit Reinders
    By Jorrit Reinders

    There is no foul play.  Companies weigh on probabilities and go ahead with the purchases. This is why large corporations have risk assessment, risk management departments.

  • Kris Lubcek
    By Kris Lubcek

    HS2 dodges Borey McBoreface

    www.theconstructionindex.co.uk

    HS2 Ltd wants the public to vote on the names of its tunnelling boring machines – but it has learned a lesson from the Boaty McBoatface incident.

image

image