https://www.hindustantimes.com/cities/others/mumbai-coastal-road-project-36-of-work-completed-against-40-target-says-bmc-101625599035790.html
The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the coastal road project, against the 40% target it had set for completion by mid-2021
https://www.hindustantimes.com/cities/others/mumbai-coastal-road-project-36-of-work-completed-against-40-target-says-bmc-101625599035790.html
Mumbai coastal road project: 36% of work completed against 40% target, says BMC
www.hindustantimes.comThe Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the coastal road project, against the 40% target it had set for completion by mid-2021