CRL TBM Dame Whina Cooper (named after the famed Maori rights campaigner) reaches the 500 metre mark. CRL release the following below. It includes some names that may be useful to some, hence I include it in full.
"
The project’s big Tunnel Boring Machine (TBM), Dame Whina Cooper, has reached the 500-metre mark on the first leg of its 1.6-kilometre-long journey from Mt Eden into central Auckland.
“This is fabulous news for the project, and for Auckland too,” says City Rail Link’s Chief Executive, Dr SeanSweeney. “It’s giving everyone a lift – there’ a lot of dedicated work behind this - and we’re telling Aucklandwe’re not going to be stopped by all the challenges the pandemic keeps throwing our way.” The TBM is currently below Symonds Street in Auckland’s uptown district. It is operated by CRL’s main contractor, the Link Alliance.
“Arriving at the 500-metre mark is an important target for tunnellers everywhere,” says Link Alliance Project Director, Francois Dudouit. “Getting there so soon after the level four lockdown ended is a greata chievement and demonstrates the persistence and hard work of our teams above and below ground to get the tunnels built.”
Dame Whina Cooper began tunnelling CRL’s southbound tunnel in late May. During the five week-long covid lockdown, the TBM continued to operate, well below full capacity, to reduce the risk of becoming trapped by the pressure of the earth around it. “We were well prepared to ramp up our work once the lockdown ended,” Mr Dudouit says.
Covid-related health and safety protocols are observed while tunnelling continues at pace operating 24hours a day, 7 days a week. Teams are working 12-hour shifts – one team of 12 on the TBM and another 12 above ground, with many others supporting the operation.
Dame Whina Cooper will soon pass under the Auckland motorway network’s Spaghetti Junction on its path towards the next important destination – CRL’s Karangahape Station. Arrival there is planned for the end of the year. The final leg of the TBM’s first drive – Aotea Station in central Auckland – will be completed earlyin the new year. Dr Sweeney says the pandemic has impacted the tunnelling programme.
“Since March 2020, and not including Auckland’s latest ongoing level 3 alert, CRL has endured 205 days of lockdowns or restricted working conditions under levels 4, 3, 2.5 and 2. By anyone’s reckoning, 205 days is still an awful lot of disruption,” he says. “But very importantly, no-one at CRL has lost sight of how important the project is for Auckland and the big changes it will bring to the people who live and work here.”
"
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.cityraillink.co.nz/media-releases-2021
Media Centre — City Rail Link
www.cityraillink.co.nzMEDIA CENTRE