English | Spanish | Dutch
Log in

Tideway cost increase is not as bad as feared

    Kris Lubcek
    By Kris Lubcek Replies (2)

    London's super sewer project announces that it is on track for completion in 2025 and declares a cost overrun of 1% -lower than expected- in their press release:

    Interim report confirms Tideway project on track for 2025 completion

     

    Tideway, the company building London’s new super sewer, remains on track to deliver the project by 2025, following the most substantial review of the programme since 2018. 

    The new sewer is designed to capture more than 95 per cent of the sewage spills that enter the river from London’s Victorian sewer system. It will have a significant impact on the water quality, making it a much healthier environment for wildlife to survive and flourish.

    The programme review, undertaken collaboratively by Tideway and key stakeholders including its main works contractors and Thames Water, looks at progress made on the project so far, taking into account the impacts of the Covid-19 pandemic, and provides an up-to-date picture of the future schedule.

    With the remaining tunnelling, secondary lining of the tunnels and shafts, and the connections to the Thames Water sewer network progressing well, the verified programme provides confidence the project will be completed in 2025. 

    Andy Mitchell, Tideway’s CEO, said: “Working closely with our contractors and Thames Water has allowed us to look in detail at our progress so far and what we need to do going forward, to complete our project and start tackling sewage pollution in the River Thames as soon as possible. 

    “This comprehensive review has reaffirmed confidence in our programme as we reach the end of the tunnelling phases and look ahead to the testing and commissioning stage. We are fully focused on delivering the Tideway project safely, at the right quality and to best value.” 

    Sarah Bentley, Thames Water CEO, said: “This joint review of progress is a positive step forward in the delivery of the Thames Tideway Tunnel. Our teams are focused on working together to complete the project and bring the tunnel into service – so that it can do the vital job of improving the health of the river Thames and London’s environment.” 

    Tideway’s interim report, published today, confirms the programme review and the resulting c1 per cent increase in costs (£39m). The project cost estimate is £4.2bn and the estimated £20-£25 annual cost range for Thames Water bill payers remains unchanged. 

    Key achievements in the period included the completion of shaft excavation on all sites and completion of 9.8km of tunnel secondary lining. Almost 24km of the new tunnel system has now been excavated under the River Thames.  

    Tideway has also started its process of handing back areas where it has finished work, with a section of land at Hammersmith Pumping Station having been successfully handed back to a residential developer.  

    To date, Tideway has transported more than five million tonnes of material by river during construction, avoiding more than 600,000 HGV journeys and saving 14,816 tons of carbon dioxide emissions. 

    image

    image