On Uznam side, work continued on building of support buildings. Work continued for Tunnel Boring Machine Starter Chamber by excavation of the area.
On the other hand, on the Wolin island side, area cleared of trees and the infrastructure on the way, electric cables etc.
It is said that despite Covid-19 Chinese company CREG is on schedule for manufacture of the TBM. Manufacture is complete to large extend. In June factory acceptance tests will be performed in China.
Please also read my recent post: Świną tunnel will be completed and operational in the second quarter of 2023
Świna tunnel (Tunel Świnoujście) progress 18-24 April 2022
Świna tunnel (Tunel Świnoujście) progress 25 April - 1 May 2022
Świna tunnel (Tunel Świnoujście) progress 2-8 May 2022
Świna tunnel (Tunel Świnoujście) progress 04.07.2022 - 10.07.2022
Świna tunnel (Tunel Świnoujście) progress 11.07.2022 - 17.07.2022
Świna tunnel (Tunel Świnoujście) progress 18.07.2022 - 24.07.2022
Świna tunnel (Tunel Świnoujście) progress 25.07.2022 - 31.07.2022
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
Świna tunnel (Tunel Świnoujście) progress March 2022 21-27 March
www.youtube.com