During last 18 years, the cost of Lowari Tunnel project has escalated mainly due to delay in execution, shortage of funding and depreciation of Pakistan rupee.
[it has been implemented in 19 years 2 months]
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.nation.com.pk/14-Sep-2022/cost-of-lowari-tunnel-project-escalates-by-475pc-to-rs46-billion
Cost of Lowari Tunnel Project escalates by 475pc to Rs46 billion
www.nation.com.pkISLAMABAD - The cost of Lowari Tunnel Project has escalated to Rs 46 billion which is 475 percent higher than the original PC-I cost approved in 2004. The original PC-I