The performance of a full face tunnel boring machine (TBM) in Tarabya (Istanbul)
Yazarlar: N. Bilgin, C. Feridunoğlu, D. Tumac, M. Çınar, Y. Palakçı, O. Gündüz & L. Özyol.
Ilk baski 2005 CRC Press Pages 8 eBook ISBN 9780429107481
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.taylorfrancis.com/chapters/edit/10.1201/NOE0415374521-130/performance-full-face-tunnel-boring-machine-tbm-tarabya-istanbul-bilgin-feridunoglu-tumac-cinar-palakci-gunduz-ozyol?context=ubx&refId=e51bbbe5-202b-4dec-9795-0c403f7f5661
The performance of a full face tunnel boring machine (TBM) in Tarabya
www.taylorfrancis.comThe groundwater level (GL) is between
11.0 m
and
5.0 m and the first section, which is about
800 m in length, is a waterless section.As of the end of December