DMRC achieves twin tunnel break through as part of phase 4 expansion

    Rohit Agarwal
    By Rohit Agarwal Replies (2)

    Two TBMs boring in parallel have emerged after "covering a length of approximately 2997 metres, at an average rate of 8.2 metres per tunnel per day".

    They were operated by Afcons Infra.

    https://www.hindustantimes.com/cities/delhi-news/dmrc-achieves-twin-tunnel-break-through-as-part-of-phase-4-expansion-101726683714949.html