Excellent reporting by ETV Bharat.
'The Srisailam project faced 4,870 days of inactivity, 460 days without electricity, and years of delays, with only 18 days of work before the accident.'
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.etvbharat.com/en/!state/years-of-delay-plague-srisailam-left-bank-canal-tunnel-project-enn25030405465
Years Of Delay Plague Srisailam Left Bank Canal Tunnel Project
www.etvbharat.comThe Srisailam project faced 4,870 days of inactivity, 460 days without electricity, and years of delays, with only 18 days of work before the accident.