Colombia to pay for cost overruns on La Linea tunnel project

    Danilo Merges
    By Danilo Merges Replies (5)

    Colombia’s national roads institute (Invias) to pay $ 9,346 million to the Consorcio Conlinea Tres consortium (Constructora Conconcreto, CSS Constructores and Estyma Estudios y Manejosfor) the La Linea tunnel project cost overruns. This comes after an arbitration tribunal decision..

    Initially, the Consorcio Conlinea Tres requested compensation for $ 15,900 million, but the Court ruling established a payment that only amounted to $ 9,346 million.

    Court information (happy reading) https://bibliotecadigital.ccb.org.co/bitstream/handle/11520/24021/5217%20CONSORCIO%20CONLINEA%203%20VS.%20INVIAS%2026%2006%202019.pdf?sequence=1&isAllowed=y

    https://www.alertatolima.com/noticias/tolima/ibague/cerca-de-9000-millones-debera-pagar-invias-tras-perder-demanda-por-tunel-de