Mumbai Metro Rail Corporation (MMRC) declares the 32nd breakthrough at Dadar Station.
Tunnel Boring Machine Krishna-2 reached the Dadar station after excavating 1.1 km and laying 791 rings.
MMRC released the following information:
Colaba-Bandra-SEEPZ Metro-3 Corridor
32nd Breakthrough at Dadar Metro Station
Mumbai, October 5, 2020 –Mumbai Metro Rail Corporation (MMRC), today, achieved 32nd breakthrough of 1.10-km long tunnel from Siddhivinayak north shaft to Dadar Metro Station in the presence of Mr. Ashutosh Kumbhakoni, Advocate General of Maharashtra. He said, "I appreciate that a monumental task is being completed while causing as little inconvenience to the public as possible. This line will be an important addition to the public transport infrastructure and a boon to Mumbaikars".
The Herrenknecht made Tunnel Boring Machine (TBM) Krishna-2, equipped with Earth Pressure Balance technology, was lowered on December16, 2019 and has completed the upline stretch in days using 791 rings.
“Today’s breakthrough was a challenging task as Dadar Metro Station –one of the more prominent stations on the Colaba-Bandra-SEEPZ corridor –is located in close proximity of residential buildings and commercial shops”, said Mr. Ranjit Singh Deol, Managing Director, MMRC.
overall progress of Dadar Metro Station is 61%. Package-4, which consists of Dadar, Siddhivinayak and Shitladevi Metro Stations, showcases overall 94% tunneling progress and 95% of the excavation work.
The total tunneling of the project completed is 87% and civil work is 60% as on today.
Mumbai Metro to achieve 8 more breakthroughs to complete 100% tunnelling
Mumbai, India (Urban Transport News): Mumbai Metro Rail Corporation (MMRC) on 16th October 2020 …
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://mumbaimirror.indiatimes.com/mumbai/other/watch-mumbai-metro-3-work-mmrc-achieves-32nd-breakthrough-at-dadar-metro-station/articleshow/78493751.cms
Watch | Mumbai metro-3 work: MMRC achieves 32nd breakthrough at Dadar metro station
mumbaimirror.indiatimes.comThe tunneling was done in presence of Advocate General GoM Shri Ashutosh Kumbhkoni and MMRC MD Ranjit Deol.