Null

English | Spanish | Dutch
Log in

Nhổn - Hà Nội tunnel boring in 2021 January-March start

 

Project Management Board of Hà Nội Urban Railways (MRB) this year get from Germany Herrenknecht Tunnel Boring Machine. Boring tunnel section of Nhổn - Hà Nội in 2021 in months of January, February, March start. Underground tunnel finish 2022 December.

Tàichính write Nhổn - Hà Nội railway 12.5km. Railway line have 4 underground stations. Other 8 stations over ground (not underground). 4.5 Km of railway underground. 8 Km of railway over ground. French trains come already in October 2020. Total project 65.91% finish. Over ground railway maybe end 2021 carry passenger.

The project cost 1,176 million Euros. ODA Loans from European Investment Bank, French Government, Asian Development Bank and domestic reciprocal capital.
 

http://thoibaotaichinhvietnam.vn/pages/kinh-doanh/2020-10-29/khoan-ngam-tuyen-metro-nhon-ga-ha-noi-trong-quy-i-2021-94260.aspx

image

image