Null

English | Spanish | Dutch
Log in

Bosnia Zenica Tunnel construction continue 24 hours / day

 

Zenica Tunnel will shorten Zenica - Žepče road by 6 kilometer.

Zenica tunnel is two tube tunnel. Each tunnel 2,4 kilometer long. Sarajevo-based Bosnian company Euro-Asfalt contruct the Zenica Tunnel. Supervision work is done by Turkish company Proyapi.

Bosnia State Road Company FB-H announce construction continue 24 hours a day. Currently progress made is: 750 meter of left tunnel and 780 meter of right tunnel excavated according to eKapija reporting.

https://www.ekapija.com/news/3064250/napreduju-radovi-na-poddeonici-ponirak-vraca-izgradnja-tunela-skratice-put-izmedju-zenice

image

image