Lonato Tunnel Boring Started

    Roberto Calvi
    By Roberto Calvi Replies (1)

    On November 14, the Earth Pressure Balance Tunnel Boring Machine "Martina" has started boring the Lonato Tunnel. The tunnel is an important part of the Milano - Venezia high speed railway.

    The Lonato Tunnel has a length of 4,75 kilometre for each of the two tubes. The tunnel has a diameter of 8,80m. Each 2m-long ring has 6 segments in it and has a thickness of 45cm.

    When the boring of the first tube is completed and breaktirhough at Verona entrance the EPB-TBM will be disassembled and will be brought to Milano entrance for boring the second tunnel.

    The "High Speed/High Capacity Milano-Verona Railway Line (Brescia East-Verona section) and related soil consolidation work from chainage 115+990 to chainage 120+772" has been awarded to SELI Overseas S.p.A with a contract amount of €204.983.361,21.

    Construction started on 28 August 2020 and estimated completion date is somewhere in August 2023.

    https://mobilita.org/2020/11/25/tav-milano-venezia-la-tbm-martina-ha-iniziato-a-scavare-il-tunnel-di-lonato/