The New York City Department of Environmental Protection has completed excavation of the 2.5-mile long Delaware Aqueduct Bypass Tunnel, a significant milestone in the $1bn effort to repair leaks in the longest tunnel in the world. Completion was marked when the JV Kiewitt-Shea’s 21.6-foot diameter Robbins TBM broke through a wall of shale bedrock nearly 700 feet beneath the Town of Wappinger in Dutchess County. Excavation of the tunnel was completed on budget and ahead of schedule.
https://tunnellingjournal.com/delaware-aqueduct-bypass-tunnel-breakthrough/
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
Here is the Robbins TBM that made it before it started the journey
TBM for the Delaware Aqueduct Bypass Tunnel
www.youtube.comThis tunnel boring machine will excavate the Delaware Aqueduct Bypass Tunnel. The cutter head turns at 8.8 rpm, max. As the machine excavates, it will partia...