North Cyprus water conveyance tunnel TBM breakthrough achieved

    M. Demir
    By M. Demir Replies (2)

    An important breakthrough for the Geçitköy-Güzelyurt water conveyance tunnel in Turkish Republic of North Cyprus.

    The length of the tunnel is 5700 meters and the diameter is 4,2 meters. The Tunnel Boring Machine is a revised machine by Turkish TBM manufacturer E-BERK.

    President of the Turkish Republic of North Cyprus (TRNC) has talked in the ceremony (video above) as well as the Turkey's Minister of Agriculture and Forestry. The tunnel costs 277 million TL.

    Currently only 9% of North Cyprus land can be irrigated. With the project this will increase to 74%.

     

    NORTH CYPRUS WATER PROJECT

    The island of Cyprus is poor in fresh water resources. Just as many islands have the problem. The Turkish part of the island (Turkish Republic of North Cyprus) is working on solution with the help of Türkiye.

    It is hoped that the project will also supply water to the South Cyprus (Greek part).

    It is a big project with many important milestones already completed.

    Turkish Republic of North Cyprus Water Project

    First water is captured in Türkiye from the Manavgat river which normally flows into Akdeniz (mediterrenean). It is then stored in Alaköprü Dam (completed).

    http://bilgi.dsi.gov.tr/projeler/kktc-su-temin-projesi/kktc.html

    Turkish Republic of North Cyprus Akdeniz Water Pipeline

    Then the water is conveyed from Türkiye to North Cyprus via an underwater suspension water pipeline. This 80 kilometer pipeline is already completed and functional. It is 250 meters below sea level.

    Then this water is stored in Geçitköy Dam (completed) in North Cyprus.

    This dam will provide 75 millon m3 water annually to North Cyprus. 38 Million m3 of this will be processed in the newly built refinement installations and will be used as drinking water. The remainin 37 million m3 water will be used for irrigation.

    Then the water in this project will be conveyed to the fields at Güzelyurt and Mesarya fields via the newly built tunnel.

    KKTC Alaköprü Dam

    https://dogruhaber.com.tr/haber/753489-kuzey-kibrista-sulanabilir-alan-yuzde-9dan-yuzde-74e-cikacak/