Świna tunnel progress: Gulermak's CREG TBM already bored 970 meters and almost through the river bed

    Teodor Adamczyk
    By Teodor Adamczyk Replies (2)

    According to progress report of The General Directorate for National Roads and Motorways, 30 meters more and the TBM will have bored under the entire riverbed of the Świna Strait and will arrive at the Wolin Island.

    https://szczecin.tvp.pl/55205990/juz-prawie-kilometr-tunel-pod-swina-coraz-dluzszy