China Communications Construction Company Limited (CCCC) to end Karnaphuli Tunnel Project excavation early than deadline.First underwater tunnel project Bangladesh.
73% of the construction work for the tunnel finish.
https://www.tbsnews.net/bangladesh/infrastructure/karnaphuli-tunnel-excavation-end-deadline-312061
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.tbsnews.net/bangladesh/infrastructure/karnaphuli-tunnel-excavation-end-deadline-312061
Karnaphuli tunnel excavation to end before deadline
www.tbsnews.netWhile work on the excavation for the first tube of the Karnaphuli tunnel was delayed by the pandemic, faster efforts for the second tube have made up for the crucial lost time as its boring is expected to end this Friday – nearly two months ahead of...