Traylor Bros gets the TRWD tunneling contract together with Sundt. Work involves TBMing! (hope with a Robbins or Akkerman).
Tarrant Regional Water District (TRWD) has selected the Traylor-Sundt Joint Venture (TSJV) to construct the IPL Section 19 Long Tunnel Crossings project (PL19TUN).
The entire IPL Project is an integrated water delivery transmission system in the Dallas area consisting of 150 miles of pipeline, three new lake pump stations, and three new booster pump stations delivering a required capacity of 350 million gallons per day (MGD) of raw water to North Central Texas. TRWD and the City of Dallas Water Utilities currently serve over 4.1 million residents and the IPL will allow these agencies to continue supporting regional community and economic growth.
The Section 19 Long Tunnel project includes two EPB TBM tunnels totaling 10,944 linear feet; two microtunneling runs totaling 1,727 linear feet; 191 linear feet of hand-mined tunnel; and installation of 84-inch-diameter carrier pipe throughout. Notice to proceed is anticipated next month, with expected completion in early 2026.
https://www.traylor.com/project-win-ipl-section-19-long-tunnel-crossings/
The EPB TBM, named Dallas, launched last June has holed through on the 457.20 m (5100-foot) Cedar Creek tunnel.
The EPB TBM, named Dallas, launched last June has holed through on the 457.20 m (5100-foot) Cedar Creek tunnel. Which is part of the IPL Section 19
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.traylor.com/project-win-ipl-section-19-long-tunnel-crossings/
Project Win! IPL Section 19 Long Tunnel Crossings - Traylor Bros., Inc.
www.traylor.comTarrant Regional Water District (TRWD) has selected the Traylor-Sundt Joint Venture (TSJV) to construct the IPL Section 19 Long Tunnel Crossings project (PL19TUN). The entire IPL Project is an integrated water delivery transmission system in the...