Bangkok Orange Line Metro tunnel breakthrough

Bangkok Metro Orange Line Breakthrough

TERRATEC’s EPBM completes Bangkok Orange Line Metro tunnel
31 March 2021

 

Earlier in March, TERRATEC joined workers and officials in celebrating the completion of the 3.3km MRT Orange Line (East section) project at Hua Mak Station. TERRATEC 6.39m diameter S70 EPB machine has been chosen by contractor Italian-Thai Development PCL (ITD) on one of three underground civil works contracts for the first 23km-long (East Section) phase of the Mass Rapid Transit Authority of Thailand’s (MRTA) Orange Line Project. The Eastbound tunnel breakthrough on Contract E3 has achieved way ahead of schedule.

Contract E3, which was awarded to ITD in May 2017, totals over 6km of TBM driven tunnel and three underground stations, extending from Khlong Ban Ma to Hua Mak. After completing the Westbound tunnel on Jan. 20, 2020 with the best month ever in Thailand with progress of 663.4m, TERRATEC S70 machine began mining eastwards from the Khlong Ban Ma station box on April 26, 2020, and quickly got up to speed following its initial drive. By mid-June 2020, the TBM was achieving the best rates of  33 rings per day (46.2m/day – another best every advance rate per day) and had already undertaken its first intermediate breakthrough.

In March 2020, The Westbound tunnel breakthrough on Contract E3 took place a full month ahead of schedule. The Eastbound tunnel breakthrough on Contract E3 has achieved 118 days ahead of schedule.

TERRATEC S70 TBM was designed to tackle the variable soft ground geology of the city – which ranges from soft and medium to stiff and very stiff clays, with lenses of dense sand and the potential for high-pressure groundwater inflows – as well as the need to mine through numerous diaphragm wall shafts and potentially, concrete piles.

In order to handle these challenging conditions, the TBM’s soft ground cutterhead features a spoke style and the addition of back-loading knife bits to assist the break-in and break-out of the shafts. In addition, the machine is fitted with an active bentonite face support injection system and double-gated screw, to ensure face stability and mitigate settlement during excavation in areas of flowing sands and high groundwater pressure.

https://www.youtube.com/embed/vyUxVuO1RwY

As the machine progresses along the alignment, it has been installing a precast concrete segmental lining consisting of five x 1400mm wide Universal style segments plus key, with an internal diameter of 5.7m. These are being produced by ITD at the same factory used for segment manufacture during its MRT Blue Line underground works contract five years ago, which also employed a TERRATEC TBM.

In total, TBM tunnelling operations for ITD’s Orange Line (East) contract has lasted two years and are being assisted at all times by TERRATEC’s highly-experienced Field Service staff – who’s quality after sales support service has created very loyal client-base in Thailand – to ensure optimum performance and successful project completion.

Bangkok’s new Orange Line will eventually total about 35.9km with 26.2km aligned underground with 22 underground stations and another 9km and seven stations on elevated structures. The line is scheduled to open in March 2024. When completes, the Orange Line will provide a vital transportation link from Bangkok’s city centre to districts in the east, reducing traffic congestion and paving the way for improved accessibility, economic growth and new residential and commercial opportunities along the alignment.

 