Contractor prepare forarrival of TBM 1 on the south shaft of Thamrin, working on jet grout, and installing a traffic deck in southern area of Thamrin Station, as well as commissioning and preparing for main drive of TBM 1 for the HI-Thamrin roundabout tunnel. Also at Monas Station, preparation for main drive TBM 2 for Monas-Thamrin tunnel continue Kompas write.
MRT Jakarta, the entire phase 2A work is targeted to be completed by March 2025.