To ensure a service life of at least 120 years for the upcoming 18km immersed tunnel between Lolland and Fehmarn, the quality of the tunnel elements has to be second to none.
To this end the contractor consortium, Femern Link Contractors, FLC, has produced a full-scale model of part of a segment comprising 1½ train tunnel tube 12m long. The trial casting lasting 30 hours was then carried out under realistic conditions.
An additional two full-scale trial castings are planned to be done. The main purpose of the full-scale trial casts is to test the process, materials and techniques, as well as gain vital experience prior to actual casting, which begins at the end of the year.
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://femern.com/press/news/trial-casting/
Successful Full-Scale Trial Cast of Tunnel Element
femern.comThe contractor consortium FLC has completed a full-scale trail casting of a segment of a tunnel element at the construction site at Rødbyhavn.