Tunnel boring machine Vida has broken the 2000 metre mark for the inbound tunnel on the West Gate Tunnel project.
Here you can see where the West Gate Tunnel Boring Machines currently are:
TBM Tracker: https://bigbuild.vic.gov.au/projects/west-gate-tunnel-project/construction/tunnel-tracker
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.trenchless-australasia.com/2023/02/06/vida-reaches-three-quarter-mark-for-the-west-gate-tunnel/
https://bigbuild.vic.gov.au/projects/west-gate-tunnel-project/construction/tunnel-tracker
Vida reaches three-quarter mark for the West Gate tunnel
www.trenchless-australasia.comThe TBM is over three quarters of the way through its journey, having bored 2013 metres and laid almost 888 of the 1014 concrete rings.