Canada: Regulator provides its reasons for Trans Mountain route change ruling

    Matt J. Scott
    By Matt J. Scott Replies (1)

    ...being forced to stick to a previously agreed upon route and construction method despite the difficulties encountered tunnelling through rock in that area would result in unacceptable delays and cost increases.

    https://www.cheknews.ca/regulator-provides-its-reasons-for-trans-mountain-route-change-ruling-1174012/