The opening of Transport for Londons (TfLs) Silvertown Tunnel has been brought forward to early 2025 while work on the cut-and-cover sections and road realignment works have hit full steam.
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.newcivilengineer.com/latest/silvertown-tunnel-opening-advanced-to-early-2025-as-cut-and-cover-and-road-realignment-progress-22-02-2024/
Silvertown Tunnel opening advanced to early 2025 as cut and cover and road realignment progress | New Civil Engineer
www.newcivilengineer.comDocuments from the February 28 meeting of TfL’s Programmes and Investments Committee reveal that the permit-to-use date of the 1.4km tunnel under the