A very good post-mortem of Melamchi water tunnel in Napal. Although this article is is mainly on the fatal accident during hydrostatic tests which killed two tunnel inspectors after a faulty water gate broke open, it has many more information over what awaits the contractors (Nepalese or foreign) when they build tunnels in Nepal. During its construction, 10 ministers changed during this time and 24 executive chairmans responsible for this tunnel changed. Contractors fired by the government and new contractors took over for construction of the Melamchi Water Tunnel. It took 20 years.
https://kathmandupost.com/columns/2020/08/17/the-morass-that-is-melamchi
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://kathmandupost.com/columns/2020/08/17/the-morass-that-is-melamchi
Opinion | The morass that is Melamchi
kathmandupost.comThe government must hold an inquiry into the tunnel disaster that killed two persons.