Bzb write The company which conduct feasibility study and design (Consitrans) proposal is too costly said the Minister of Transport, Sorin Grindeanu, said in a televised broadcast. He said the reason for high cost is too long tunnels.
He said "When I became Minister of Transport, the situation I found as follows: Tender for the Feasibility Study and Technical Project, the duration of which is about 5 yearswas awarded. Routes discussed with with Consitrans. He said to come up with 8 billion euro cost for 100 km of highway with more than half of the route is tunnels".
Consitrans tender is 30 months is for for the feasibility study and another 6 months for design.
European Union will contribute for 85% to the cost.
Ministrul Transporturilor, Sorin Grindeanu, a declarat că nu se poate ca autostrada Comarnic-Brașov să coste 8 miliarde de euro și că trebuie găsit un echilibru. „Nu se poate, și este părerea mea, să venim cu variante care să ne ducă într-un final...
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://bzb.ro/stire/autostrada-ploiesti-brasov-jumatate-prin-tunel-ministerul-transporturilor-si-cnair-nu-accepta-primul-traseu-de-8-miliarde-de-euro-a178043
Autostrada Ploieşti - Braşov, jumătate prin tunel: Ministerul Transporturilor şi CNAIR nu acceptă primul traseu, de 8 miliarde de euro | Buna ziua Brasov