Nepal: Nagdhunga Tunnel digging halted for 20 days

    Ravnish Sharma
    By Ravnish Sharma Replies (1)

     

    Construction halted after machines damaged. Media report 4-5 meter daily progress before the halt.

    Construction come from both ends of Dhading and Kathmandu for Nagdhunga Tunnel. So far 50,5% progress reported.

    The tunnel is 2.7 km long 12 meter wide 8 meter high. Construction started late because because Nepal Army did not grant permission for import of explosives for constructor Japan’s Hajma Ando Corporation. Then after came COVID_19 pandemy.

    https://myrepublica.nagariknetwork.com/news/nagdhunga-tunnel-digging-halted-for-20-days/?categoryId=81