Construction halted after machines damaged. Media report 4-5 meter daily progress before the halt.
Construction come from both ends of Dhading and Kathmandu for Nagdhunga Tunnel. So far 50,5% progress reported.
The tunnel is 2.7 km long 12 meter wide 8 meter high. Construction started late because because Nepal Army did not grant permission for import of explosives for constructor Japan’s Hajma Ando Corporation. Then after came COVID_19 pandemy.
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://myrepublica.nagariknetwork.com/news/nagdhunga-tunnel-digging-halted-for-20-days/?categoryId=81
Nagdhunga Tunnel digging halted for 20 days
myrepublica.nagariknetwork.comKATHMANDU, April 5: Digging work under the Nagdhunga Tunnel Construction Project in Kathmandu has been halted for 20 days after digging devices got damaged.