Ministry of Public Works, Transport and Housing of Canaries has already obtained all environmental permits to use explosives for excavation of the tunnels in Gran Canaria. Until now, contractors had been using mechanical means for excavation for the tunnels through the Faneque mountain range but progress has been slow. Only 150 meters of the total 5 kilometres has been excavated.
With the new permit excavation will speed up with explosives and will continue on 24-hour shifts.
Hopefully with the new technique the consortium of Acciona, Ferrovial Agroman, Lopesan Asfaltos y Construcciones and Bitumex will perform better to finish the tunnel in two years. The new road which will cost €152 million will shorten the travel time between La Aldea and Agaete to 12 minutes from current 25 minutes writes Qué!
Blasting began in the tunnels of the second phase of the La Aldea road. Until now mechanized tunnelling used.
In addition to blasting, the contractor consortium Acciona, Ferrovial, Lopesan and Bitemux have 5 “jumbos” to drill the rock.
Según ha podido saber Foro Roque Aldeano, durante la jornada de hoy se han iniciado las voladuras en los túneles de la segunda fase de la carretera de La Aldea. Las perforaciones mediante explosivos, que hasta el momento se venían llevando a cabo...
North and South excavating teams of Gran Canaria's Guguillo tunnel expect to meet each other in middle of May.
https://tunnelcontact.com/discussion/view/32831/gran-canarias-guguillo-tunnel-excavation-nearing-end
The Networking Site for Tunnel and Underground Space Professionals
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.que.es/ciudades/canarias/el-gobierno-impulsa-las-obras-de-la-carretera-a-la-aldea-con-turnos-de-24-horas-y-voladuras-en-los-tuneles.html
El Gobierno impulsa las obras de la carretera a La Aldea con turnos de 24 horas y voladuras en los túneles
www.que.esEl consejero Sebastián Franquis informa en el Parlamento que la Consejería de Obras Públicas, Transportes y Vivienda ha obtenido ya todos los permisos medioambientales para habilitar polvorines y utilizar los explosivos en los trabajos de...