17,5 km Anding Tunnel with the most complex geological conditions on China-Laos-Kunming-Wanzhou Railway finish September 30

    Chu Yang
    By Chu Yang Replies (2)

    17,5 km Anding Tunnel with the most complex geological conditions and most difficult construction on the China-Laos-Kunming-Wanzhou Railway finish September 30.

    Xinhuanet report on July 26, two inclined shafts (2-1 and 2-2 inclined) are connected.Anding Tunnel is on collision zone of Indian Ocean plate and the Eurasian plate. It crosses the Ailao Mountain and has complex geological conditions.

    Anding Tunnel is a very high-risk tunnel with 21 faults on its way. Mainly IV and V grade soft rock. The China Railway Fifth Bureau is responsible for construction.

    http://big5.xinhuanet.com/gate/big5/www.yn.xinhuanet.com/newscenter/2020-08/09/c_139276413.htm