Inspection approve 4,908.57 metre water tunnel. It is in use on July 21. Diameter 3,9 metre.
Acceptance Council has Da Nhim-Ham Thuan-Da Mi Hydropower Joint Stock Company as the Investor; The supervision consultant is Joint Venture Nippon Koei-PECC3-Nippon Koei Vietnam; Design consultant is Electrical Construction Consulting Joint Stock Company 2; The construction package contractor is Construction Joint Stock Company 47 and hydraulic mechanical package contractor is the NARIME - COMA Joint Venture.
Tunnel construction is partial TBM boring and partial blast method. On March 23, 2019 at 3,739.51 metre boring tunnel slippage happen when TBM go through a weak geologic area. Decision was to tunnel rest of tunnel 929.05 metre with blast method and not TBM method.
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://www.vietnamplus.vn/duong-ham-dan-nuoc-du-an-mo-rong-da-nhim-hoan-thanh-vuot-tien-do/728085.vnp
Đường hầm dẫn nước Dự án mở rộng Đa Nhim hoàn thành vượt tiến độ | Kinh doanh | Vietnam+ (VietnamPlus)
www.vietnamplus.vnSau khi kiểm tra toàn bộ đường hầm với chiều dài 4.908,57m từ cửa nhận nước đến nhà van, Hội đồng nghiệm thu đã thống nhất đưa đường hầm vào sử dụng từ ngày hôm nay (21/7), vượt tiến độ 6 ngày.