As of August 25, Construction of MRT Jakarta Phase 2A of CP 201 Reached 42.69 Percent

    Yi  Wei
    By Yi Wei Replies (1)

    Construction of  MRT Jakarta Phase 2A of CP 201 go fast with high quality Japanese Tunnel Boring Machines. With all aspects, as of August 25, 42.69% progress done.

    Phase 2A of MRT Jakarta will connect the HI Roundabout Station to Kota for about 5.8 kilometers and has 7 underground stations: Thamrin, Monas, Harmoni, Sawah Besar, Mangga Besar, Glodok, and Kota.

    Phase 2A is divided into two segments: Segment 1 of the HI-Harmony Roundabout to be completed  for March 2025, and Segment 2 of Harmoni-City to be completed in August 2027.

    Phase 2A of the Jakarta MRT to cost Rp. 22.5 trillion through a cooperation loan between the Governments of Indonesia and Japan.

    Construction of Monas Station is now platform level casting work, station column casting/wall structures, completion of column drilling at substations, completion of tunnel boring from Monas to Thamrin, and preparation of northbound drilling for TBM-2 from Thamrin Station to Monas Station.

    At Thamrin Station, work continues for retaining wall and station wall (D-Wall), TBM-1 breakthrough preparation work and preparation for -turn on station shaft,.

    Phase 2B of MRT Jakarta, which is planned to continue from Kota to Ancol Barat Depo, is still ongoing. in the feasibility study stage.

    https://jakartamrt.co.id/id/info-terkini/25-agustus-pembangunan-fase-2a-cp-201-capai-4269-persen