Świna tunnel progress Sporadic weekly.

 

On Uznam side, work continued on building of support buildings. Work continued for Tunnel Boring Machine Starter Chamber by excavation of the area.

On the other hand, on the Wolin island side, area cleared of trees and the infrastructure on the way, electric cables etc.

It is said that despite Covid-19 Chinese company CREG is on schedule for manufacture of the TBM. Manufacture is complete to large extend. In June factory acceptance tests will be performed in China.

 