On Uznam side, work continued on building of support buildings. Work continued for Tunnel Boring Machine Starter Chamber by excavation of the area.
On the other hand, on the Wolin island side, area cleared of trees and the infrastructure on the way, electric cables etc.
It is said that despite Covid-19 Chinese company CREG is on schedule for manufacture of the TBM. Manufacture is complete to large extend. In June factory acceptance tests will be performed in China.
Świna tunnel progress: Gulermak's CREG TBM already bored 250 meters
The Networking Site for Tunnel and Underground Space Professionals
Świna tunnel (Tunel Świnoujście) progress 26 April - 2 May 2021.
Świna tunnel (Tunel Świnoujście) progress 3-9 May 2021
Świna tunnel (Tunel Świnoujście) progress 10-16 May 2021.
Świna tunnel (Tunel Świnoujście) progress 17-23 May 2021.
Świna tunnel (Tunel Świnoujście) progress 24-30 May 2021.
Świna tunnel (Tunel Świnoujście) progress 31 May - 6 June 2021.
Tunnel Boring Machine is now boring under the water for Świna tunnel (Tunel Świnoujście).
Świna tunnel (Tunel Świnoujście) progress 7-13 June 2021.
Swina Tunnel excavation reaches 507 meters.
507 metrów, tyle do tej pory wydrążył TBM Wyspiarka. Maszyna weszła już pod cieśninę Świny, a swoją
Świna tunnel (Tunel Świnoujście) progress 14-20 June 2021.
Świna tunnel (Tunel Świnoujście) progress .
170 1,5m and 154 2m rings already installed by the TBM. This means that the bored tunnel has reached a total of 563 meters. Last week, the TBM installed another 13 two-meter rings.
https://www.swinoujskie.info/2021/06/28/raport-z-postepu-prac-przy-drazeniu-tunelu-w-swinoujsciu/
170 półtorametrowych i 154 dwumetrowych – tyle docelowych pierścieni zamontowała już Wyspiarka. Ozna
Świna tunnel (Tunel Świnoujście) progress 21-27 June 2021.
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
Tunel Świnoujście - Świna tunnel progress 12-18 April 2021
Voordat je verdergaat naar YouTube
www.youtube.com