Nagdhunga-Naubise tunnel construction sees 27 percent work progress

    Ravnish Sharma
    By Ravnish Sharma Replies (1)

    Katmandu Naubise by Tulsi Bhagat WCC licence

    Construction of 2.69-kilometre-long Nagdhunga-Naubise Katmandu tunnel is 27% complete with 37% of budget spent according to Nepal press. That is 736 meter dug total from both ends.

    Project cost is estimated around  $188.19 million. $141.41 million financed by Japan International Cooperation Agency (JICA) as a loan of to Nepal government.

    https://myrepublica.nagariknetwork.com/news/nagdhunga-naubise-tunnel-construction-sees-27-percent-work-progress/