Construction of 2.69-kilometre-long Nagdhunga-Naubise Katmandu tunnel is 27% complete with 37% of budget spent according to Nepal press. That is 736 meter dug total from both ends.
Project cost is estimated around $188.19 million. $141.41 million financed by Japan International Cooperation Agency (JICA) as a loan of to Nepal government.
cover tunnel photo by: Matt Brown from London, England / CC BY
Copyright 2019-2024 TunnelContact.com
https://myrepublica.nagariknetwork.com/news/nagdhunga-naubise-tunnel-construction-sees-27-percent-work-progress/
Nagdhunga-Naubise tunnel construction sees 27 percent work progress
myrepublica.nagariknetwork.comKATHMANDU, Jan 6: Around 27 percent construction work of Nagdhunga-Naubise tunnel road has been completed.