Welcome to the surface! E-BERK's TBM with E-BERK Cutting Tools breaks out to the daylight after a 4716m long, 4,98m diameter tunnelling.
DSİ Pamukluk Dam water conveyance project. Mersin, in the Mediterrenean cost of Türkiye.
It is a Robbins Double Shield with a diameter of 5,06 meters.
It is reported that it bored 12,2 km in 18 months `8 months ahead of schedule' and with a progress of '1.000 m per month' (this is what Robbins says).
I think a good deal of the tunnel under the English channel has been dug with TBMs. But these last points were dug manually and there you go! Two sides meet each other under the sea!